Project Finance & Control

Project Finance & Control — Quick Review

8 sections · About 7 minutes to read

Liam Smith · Robert Caldwell · Five lectures, September 16–30, 2026 · Workbook v8.0
Version 1.1 · 5 October 2026. Includes the supplied Modules 1/2, 3 and 4 reviews. References below are PDF-viewer pages; lecture times are recording positions. Use the complete guide for explanations and the source index for corrections.

The course in one pass

Financial management: plan → estimate → budget → control. Procurement: plan → conduct → control. Control setup: factors/thresholds → actual-data collection → change process → responsibilities → document/communicate. Ongoing control: collect → compare/analyze → act → make authorized revisions → report. (Workbook, PDF pp. 19, 139, 141, 179.)

Strategic objectives concern future organizational position; financial objectives concern financial performance. Use both. Numeric does not automatically mean financial. Project outcomes and benefits can continue after delivery. WACC represents financing cost/required return, not actual project ROI. (Workbook, PDF pp. 21–28.) (Sep 16, 01:06:04–01:46:33; segments 90–116.)

Formula card

Topic Formula Remember
WACC w_Dk_D(1-T)+w_Ek_E Financing proportions sum to 1
Capital charge Capital × WACC Specify the period
Present value F/(1+r)^t Discounted future amount
NPV -C_0+\sum C_t/(1+r)^t Includes initial outflow
Triangular estimate (O+M+P)/3 Equal weighting
PERT estimate (O+4M+P)/6 Four weights on most likely
PERT spread approximation (P-O)/6 Same units as estimate
Risk expected value Probability × impact Use a decimal probability
Course contingency Sum of residual risk expected costs Expected amount, not worst-case loss
Cost baseline Work budget + contingency Management reserve excluded
Total project budget Baseline + management reserve Separate authorization

(Workbook, PDF pp. 28–29, 61–63, 76, 79–81.)

Estimates and quality costs

Estimate class Course range
ROM −50% / +100%
Budgetary −10% / +25%
Definitive −5% / +10%

Analogous = compare similar previous work. Parametric = quantity/rate or calibrated historical model. Bottom-up = detailed estimates rolled upward. Modified Delphi = independent expert estimates, discussion and revision toward consensus. Method and estimate class are different ideas. (Workbook, PDF pp. 60–61, 76–77.)

Conformance: prevention (training/planning) and appraisal (testing/inspection). Nonconformance: internal failure (scrap/rework before delivery) and external failure (returns/warranty after delivery). Extra precision is not extra accuracy. Check overhead bases and avoid counting the same contingency twice. (Sep 21, 01:13:49–03:00:51; segments 128–150, 192–203.)

Earned-value card — highest recall priority

PV = budget for scheduled work. EV = budget value of performed work. AC = actual cost. BAC = total approved baseline budget; BD = total baseline duration. Compare all three at the same status date. Financial PV means present value; EVM PV means planned value. Risk expected value is not earned value. (Workbook, PDF pp. 89–91.) (Sep 23, 01:13:50–01:22:00; segments 90–97.)

Schedule Cost
SV = EV − PV CV = EV − AC
SPI = EV / PV CPI = EV / AC
RTD = BD / SPI EAC = BAC / CPI

EV first in variances and indices. Positive variance or index >1 is favorable on that dimension; negative or <1 unfavorable. SV/CV are currency, indices are ratios, RTD is time, EAC currency. RTD/EAC are total forecasts, not amounts remaining. Use unrounded indices. Their continuation assumptions need checking. (Workbook, PDF pp. 111–113.)

SPI CPI Meaning
>1 >1 Ahead; favorable cost efficiency
<1 >1 Behind; favorable cost efficiency
>1 <1 Ahead; unfavorable cost efficiency
<1 <1 Behind; unfavorable cost efficiency

For graphs: EV versus PV gives schedule; EV versus AC gives cost. Actual spending versus planned spending without EV is insufficient for CPI/SPI. (Workbook, PDF pp. 107–113, 213.)

Checked anchor examples

  • Widgets: PV=$5,000, EV=$3,000, AC=$7,000; BAC=$10,000, BD=10 weeks. SV=−$2,000; SPI=.60; CV=−$4,000; CPI=3/7; EAC=$23,333.33; RTD=16.67 weeks.
  • Workbook Practice 5: EV65/PV50/AC45, in $m; BAC100m, BD100 weeks. SPI=1.30, RTD=76.92 weeks, CPI=65/45, EAC=$69.23m. The printed SPI denominator 40 is wrong.
  • Workbook Practice 6: EV45/PV50/AC55; SPI=.90, CPI=45/55, EAC=$122.22m, RTD=111.11 weeks.

(Sep 23, 00:10:35–01:10:22; segments 41–89.) (Workbook, PDF pp. 105–106.)

Percentage trap: SPI=.60 means 60% of planned budgeted work achieved; a BD/SPI projection is 66.67% longer, not 40% longer. CPI=.428571 means 42.86 cents earned per dollar spent. 1−CPI is a shortfall measured against AC; spending above EV is 1/CPI-1, here 133.33%. Specify the denominator.

Controls and decisions

A factor states what to measure; a threshold states acceptable deviation. “Cost” alone is not a metric. Define measurement point, comparator, units, owner, data source and cadence. Measurable effort has a tangible result and completion schedule. Levels mean activities, deliverables, milestones and phases, not severity tiers. (Workbook, PDF pp. 128–130, 139–142.) (Sep 28, 00:18:09–01:16:58; segments 37–77.)

At ±5%, +7% is 2 percentage points beyond the band. “40% complete ±5 percentage points” means 35–45%. Numeric thresholds are project-specific. Workbook reserve ranges and CPI alert levels are illustrations, not mandatory rules. (Workbook, PDF pp. 63, 79, 92, 114.)

Executing: do work. Monitoring: collect, measure, report. Controlling: compare, analyze, decide and take authorized action. A forecast update does not automatically change the baseline. (Workbook, PDF pp. 150, 157.)

Change: document/log → evaluate need → analyze effects → accept/reject/defer → notify → integrate approved change → implement/verify/close. CCB = authorized decision maker(s). Defer = postpone; escalation = refer for authority. Configuration control keeps product characteristics, versions and records aligned. Scope creep and gold plating are warning signs. (Workbook, PDF pp. 132–134, 144–146.)

Corrective action must respect scope, time, cost, quality, resources, risk and current stakeholder priorities. Review the critical path before moving people or crashing. Preserve essential acceptance testing; if priorities are unclear, get stakeholder agreement. “Cheapest” and “fastest” are not self-sufficient justifications. (Workbook, PDF pp. 161–164, 217–220, 247.)

Procurement card

Buyer = purchaser/client; seller = vendor/contractor. Make/buy compares internal and external options. SOW describes clear, measurable work; it may be part of a contract. (Workbook, PDF pp. 168–170, 181–183.)

Type Recall
FFP Fixed agreed price for defined scope; seller bears more cost-overrun risk
FPIF Fixed-price incentive structure
FP-EPA Defined economic price adjustment; workbook addition
CPFF Reimbursed allowable costs plus fixed fee; total price is not fixed
CPIF Reimbursed allowable costs with formula/objective incentive fee
CPAF Reimbursed allowable costs with evaluated performance award
CPP/CPPC Fee as percentage of costs; US federal FAR prohibition
T&M Fixed labor rates, variable hours/materials; manage quantities and ceilings

Risk allocation follows actual terms; “all risk” or “no risk” is too absolute. The federal prohibition is for cost-plus-percentage, not all cost reimbursement. (Workbook, PDF pp. 171–172, 185–186.) See FAR 16.102.

IFB = comparable specified work, commonly price driven. RFP = proposed solutions evaluated across criteria. RFQ = quotation. RFI = information. Bidder conference = buyer-led clarification before bid submission, not seller pitches. Validate bids before consistent evaluation; establish criteria in advance. (Workbook, PDF pp. 173–174, 188–191.)

BATNA = best alternative to a negotiated agreement, your best option if no deal occurs. Prepare interests, limits and alternatives; seek a fair relationship. Privity identifies contractual parties. Recognize pressure tactics without assuming deception is good practice. (Workbook, PDF pp. 192, 197.)

Contract control tracks performance and authorized amendments. Closeout = verify acceptance, settle financial obligations, complete records/reports, review and retain lessons. (Workbook, PDF pp. 176, 194–196.)

New module-review recall

Cost-management benefits: expectations, efficient resources, profit, capacity for further projects, learning. Implementation costs: infrastructure, training, time. CBA: identify → monetize costs → monetize benefits → discount as appropriate → evaluate. (Module review: Finance M1 M2 Review MASTER.docx, body blocks 44–53, 151–156.)

Review case Answer to remember
$100,000 estimate ROM $50k–$200k; budgetary $90k–$125k; definitive $95k–$110k
Gym: minimum 2, most likely 3, maximum 5 Triangular 3.33; PERT 3.17 visits/week
$200m headquarters, five listed risks Contingency $15.9m; baseline $215.9m if work excludes reserve
Three risks: 10%/$200k, 20%/$100k, 35%/$40k Contingency $54k

(Module review: Finance M3 Review MASTER.docx, body blocks 50–81.)

The Module 4 answer key is incorrect for several terms: performed budget = EV; incurred cost = AC; scheduled budget = PV; completion budget = BAC. Its EAC expression should be BAC/CPI when current efficiency continues. A definitive estimate is still a forecast, and EVM means Earned Value Management. (Module review: Finance M4 Review MASTER.docx, body blocks 20–22, 29.) (Module review: Finance M3 Review MASTER.docx, body blocks 5, 18.)

Last-minute corrections to retain

  1. WACC is not actual ROI; capital plus a charge is not NPV.
  2. Refinery discounted inflows=$93.264m; true NPV after $100m outlay=−$6.736m.
  3. Practice 5 SPI=65/50, not 65/40.
  4. EV does not tell you actual cost; AC/PV alone does not tell you earned-value performance.
  5. Management reserve is outside the course baseline.
  6. Percentage shortfalls need denominators; duration forecasts use reciprocal SPI.
  7. Deferred change is not necessarily escalated change.
  8. A sponsor's suggested scope cut still requires impact analysis and authorization.
  9. Fixed unit rates do not fix a T&M total; CPFF fixes the fee, not the costs.
  10. BATNA is the no-deal alternative, not your list of concessions.

Work the practice set from memory, then review its explained answers.